Updated 10 October 2026Checked against the SAMM: 26 October 2026

A case under the Accelerated Case Closure Procedures has an estimated closure date 24 months after projected final delivery or service performance, and every except a carries a note giving its estimated closure date. A case is Supply/Services Complete after final delivery, and the partner may still submit a for 12 months after delivery. Closure inhibitors identify the conditions that keep a case from being certified and closed.

AFTER THE LAST DELIVERY: HOW A CASE CLOSES fmsedge.com A partner may submit an SDR for 12 months after delivery, even once the case is Supply/Services Complete; after that, cases close. SAMM C16.3.1.1.1.1 ACCP: COUNTRIES WITH FMF-FINANCED CASES, AND COUNTRIES THAT ELECT IT NOT IN ACCP: NATIONAL-FUNDS PROGRAMS THAT DID NOT ELECT IT, AND BPC Supply/Services Complete (SSC) after final delivery; reconciled, then submitted for closure SAMM C16.3 · C16.3.1.1.1.1 Interim closure USG goal: within 24 months of SSC; 36 months for training cases; purchaser funds wait in the CCSA SAMM C16.3.1.1 · C16.3.1.1.3 Final closure if no ULO invoices arrive within four years of SSC, the IA must move the case to final closure SAMM C16.3.1.1.5 · C16.3.1.1.5.1 Funds returned excess CCSA funds stay for late claims until nine years after the original SSC, then go to the purchaser's holding account SAMM C16.3.1.1.5.2 Final closure the LOA estimates closure 36 months after the longest underlying contract closes (where contracts apply) SAMM C16.3.1.2 · C16.3.3 Legacy cases, either row implemented in fiscal year 2017 or earlier: final closure no later than September 30, 2027, unless exempted SAMM C16.4.1 · C16.4.2 · C16.4.3 In ACCP, the LOA's estimated closure date is 24 months after projected final delivery or service performance (SAMM C16.3.3). An ACCP case whose unliquidated obligations equal zero is closed direct to final, skipping interim closure (SAMM C16.3.1.1.2). A legacy case that can neither close by the deadline nor qualify for an exemption may continue under a memorandum for record (SAMM C16.4.5). Positions show sequence, not elapsed time. FMS Edge closure step · interim closure: ACCP only · legacy cases only fmsedge.com · Current as of 11 September 2026 · SAMM C16.3 · C16.4 · DSCA 26-84 · 26-95 · 26-96

A case closes after it is Supply/Services Complete (SSC). Under Accelerated Case Closure Procedures a case is usually closed first on an interim basis while funds are held for its open obligations; if no invoices arrive within four years of SSC it must move to final closure, and funds still held go to the purchaser's holding account nine years after SSC. Other cases close once, after their contracts close.

How a Foreign Military Sales case closes · Current as of 11 September 2026 · SAMM C16.3 · C16.4 · DSCA 26-84 · 26-95 · 26-96 · Download PNG

How long does it take to close a Foreign Military Sales case?

For a case under the Accelerated Case Closure Procedures (), the estimated closure date is 24 months after the projected date of final delivery or service performance. For a non- case, it is estimated at 36 months after the longest underlying contract closes, if contracts apply. If no contracts apply, the closure date should fall within 36 months after final delivery or service performance. Cases with long-running contracts may face closure challenges. On every except a I , the must include a note that gives the estimated case closure date. Appendix 6 sets out the exact wording of that note [SAMM ].

cases are marked Supply/Services Complete () after the final delivery of defense articles, and the will then carry out final reconciliation actions and prepare the cases for closure. A partner may submit a for 12 months after defense articles or services are delivered, and a case's move into status does not by itself stop the partner from doing so. Under the , cases will be closed once that period has passed [SAMM ].

Cases implemented on or after October 1, 2017 ( 2018) are also subject to case closure performance standards, which need to be met at the 85 percent level [SAMM ]. The first standard spans the time from the CLOSHOLD milestone, which the posts, to the day the submits its closure certificate to the Defense Finance and Accounting Service (). That step is shown by the CLOSE milestone in the Defense Management System (), which follows the estimated closure dates of 24 months for cases and 36 months for training cases and non- cases [SAMM ].

The second standard spans the time from the complete closure certificate to final closure, and posts the FINCLOSE milestone within 30 days of the certificate [SAMM ]. When a case exceeds the standards, the must enter reason codes in aligned to the closure metrics. The reasons in Table AP7.C4.T5 should be used, and other reasons can be used, such as contract delays, contracts in litigation or transportation delays outside U.S. Government control [SAMM ].

Several sets of closure inhibitors identify conditions that prevent cases from being certified and closed. prescribes a standard set of pre-certification inhibitors, which identify the conditions that keep a case from being certified for closure. They are set out in the Case Reconciliation and Closure Guide at Table AP7.C3.T5, and the ' automated management systems have corresponding inhibitors to varying degrees. A further set of post-certification inhibitors identifies the conditions that keep the case from being closed. Section C16.3.9.1 gives more information on that set [SAMM ].

While closure is the final phase in the case life cycle, reconciliation should occur throughout the life of the case, starting with implementation [SAMM ]. Reconciliation refers to the financial and logistical actions that ensure the following [SAMM ]:

  • Proper accounting
  • Accuracy and thoroughness of data
  • Currency of schedules
  • Timeliness and completeness of reporting

Each case manager must perform an annual case and review or reconciliation on each case. Case managers should not wait until a case is ready to be closed to reconcile it [SAMM ]. Successful reconciliation throughout the life of a case expedites case closure [SAMM ].

References

SAMM

Facts referenced

DSCA policy memoranda

  • DSCA 26-01: Performance Standards for Foreign Military Sales Case Closure
  • DSCA 26-75: Foreign Military Sales Metrics Security Assistance Management Manual Update [SAMM E-Change 845]

Related