How long does it take to get a Foreign Military Sales Letter of Offer and Acceptance?

Updated 26 October 2026Checked against the SAMM: 2 November 2026

The case development standard is to offer 85% of documents within 30 days to 130 days, depending on the case development category, counted from the date the request is actionable or, for Category D, from its receipt. A hold on a document does not stop the clock, and for a defined order document the should enter an extenuating-factor code, which moves the document to Category C, once it determines that its ability to meet the Category B standard will be affected.

CASE DEVELOPMENT: WHO HOLDS THE LOA, STATUS D TO O fmsedge.com How long does it take to get a Foreign Military Sales Letter of Offer and Acceptance? Case development standard (SAMM Table C5.T9), met by 85% of documents: Category A 30 days · Category B 90 days · Category C 130 days The clock starts at LOR Actionable (Categories A, B and C) and stops at Offer. What are the steps of FMS case development?DDevelopmentDSTATUS W Write WSTATUS R Review RSTATUS P Proposed PSTATUS LOA Offered in Foreign Military SalesOOfferedOSTATUS · OFFERED HELD BY Implementing Agency (IA) Builds the LOA data (LOAD) in DSAMS: case lines, pricing and availability, releasability, notification data. Waivers and special approvals are finished first. After its quality review, the IA posts MILAP. SAMM C5.6.9.1 · C5.6.11.1 HELD BY DSCA (IOPS/GEX/CWD) Case Writing and Development Assembles the LOAD and does final preparation of the document, then a final quality assurance review before it moves to Review. SAMM C5.6.11.6 HELD BY DSCA HQ and the IA review in the Case Tracking System CWD uploads the final version for review. The required DSCA HQ offices approve in CTS; the IA approves by posting MILSGN. Then it is Proposed. SAMM C5.6.11.7 Foreign Military Sales Arms Transfer Office (State Department)HELD BYState (PM/RSAT)when State approval is requiredGoes on the daily State FMS List for State review and approval: required for LOAs and for Amendments that add or increase scope.SAMM C5.6.11.8 · C5.6.11.8.1 HELD BY Implementing Agency (IA) DSCA countersigns (DCSGN) on State's approval; DSAMS then sets Offer status. The IA signs and offers It signs the LOA and sends it to the purchaser, through the SCO as appropriate. SAMM C5.6.11 · C5.6.11.9 · C5.6.2 returned for corrections: back to Development for the IA (SAMM C5.6.11.6.1 · C5.6.11.7.3) A Modification goes from countersignature to Implemented status, not Offered (SAMM C5.6.11). Category D (Building Partner Capacity) documents are timed to BPC Wait, not Offer (Table C5.T9). Positions show sequence, not elapsed time. Status codes are the DSAMS milestones of SAMM Table C5.T14. FMS Edge status in DSAMS · Offered: the clock stops · only when a document is returned fmsedge.com · Current as of 26 October 2026 · SAMM C5.6.2 · C5.6.9 · C5.6.11 · C5.T9 · C5.T14 · C5.T15

While a Letter of Offer and Acceptance is being prepared it moves through five statuses in DSAMS, from Development to Offered. The case development standard, counted from LOR Actionable to Offer, is 85% of documents within 30 days for Category A, 90 days for Category B and 130 days for Category C.

Who holds the Letter of Offer and Acceptance: status D to O · Current as of 26 October 2026 · SAMM C5.6.2 · C5.6.9 · C5.6.11 · C5.T9 · C5.T14 · C5.T15 · Download PNG

How long does it take to get a Letter of Offer and Acceptance?

Table C5.T9 sets the case development standard: 85% of documents offered within 30 days for Category A, 90 days for Category B and 130 days for Category C from Actionable, and within 60 days for Category D from Receipt [SAMM ]. Category D, for Building Partner Capacity () cases, stops at Wait, and for Title 10 funded cases under the Long Term Solution its clock starts at Customer Request Complete; Category A covers blanket order cases and , Category B defined order cases and Category C defined order cases with an extenuating factor [SAMM ]. The time required also depends on the type of case being prepared and the complexity of the program. Receiving comprehensive that accurately reflect international partner requirements is important to successful accomplishment of these goals.

At least one reason code from Table C5.T10 must be used for each document that misses its standard, whatever its category: reason codes record the concrete reasons a standard was not met, while a Case Development Extenuating Factor anticipates a delay and assigns Category C [SAMM ].

The Defense Management System () allows holds and suspensions to be placed on documents, but they cannot be used in place of returning a document or of moving it through the process in a timely manner. A hold does not stop the clock, and the time a case spends on hold is included in the time calculations for the processing metric [SAMM ].

In case development status, the is responsible for developing the and for its initial quality assurance. The loads the into and builds the basic structure of the there, including pricing and availability, the individual case lines, releasability coordination, notification data under Section 36(b) of the where appropriate, manpower worksheets and other related supporting documents. Every waiver, all releasability coordination and any special approval should be finished before the goes to the Case Writing and Development Division of the for final processing. The should also carry out a quality review of the before submitting it [SAMM ].

In addition to the , 's Case Writing and Development Division ( (/GEX/CWD)) plays a role in case development. Once the has finished the process for a basic , amendment or modification, and its own quality review of the package, it will post the approval () milestone in . Posting the milestone moves the document from Development to Write status and opens a case record on the case-tracking dashboard, where the uploads the offline documentation for transmission to (/GEX/CWD) [SAMM ]. The package the submits to (/GEX/CWD) with the draft must include the , a Manpower and Travel Data Sheet when the document includes case-funded manpower, the documentation for any waivers, and the cover memorandum [SAMM , , , ]. (/GEX/CWD) then completes the writing process by accomplishing a quality review for policy compliance and by adding the and the standard notes [SAMM , ]. After finalizing the document, (/GEX/CWD) staffs it for the , headquarters , and legal reviews as appropriate [SAMM , ]. When this coordination process is complete, (/GEX/CWD) adds the to the daily List for 's review and approval. Once approves, (/GEX/CWD) electronically countersigns the , and the is offered to the international partner [SAMM , ].

Once the has posted the milestone, the case record and the offline documentation it submitted move to (/GEX/CWD) in the application for processing. Various reports that (/GEX/CWD) uses show when case documents have moved to Write status [SAMM ].

should use Management Flags to give notice, at a minimum, when has countersigned a document (milestone DCSGN), when (/GEX/CWD) has returned it from Writing Status (milestone DSA CWDDOCRTN) and when has returned it from Review Status (milestone WDOCRTN). A WDOCRTN milestone sends a case back to Writing Status for corrections, and (/GEX/CWD) then returns it to Case Development status so that the can make them [SAMM ].

Try the tool: Case timeline estimator