How is a Foreign Military Sales case closed?
Once a case is Supply/Services Complete and reconciled, it is submitted for closure under Accelerated Case Closure Procedures () or under non- procedures. can close a case while obligations remain open. The sends a closure certificate to the Defense Finance and Accounting Service () in Indianapolis and processes a C1 transaction, and then closes the case in the .
A case closes after it is Supply/Services Complete (SSC). Under Accelerated Case Closure Procedures a case is usually closed first on an interim basis while funds are held for its open obligations; if no invoices arrive within four years of SSC it must move to final closure, and funds still held go to the purchaser's holding account nine years after SSC. Other cases close once, after their contracts close.
How is a Foreign Military Sales case closed?
Once a case is Supply/Services Complete (), and the requisite verification steps for reconciliation are complete, the case is eligible to be submitted for closure. Case closure is the final phase of the case life cycle and is important to the U.S. Government () and international partner. A case is submitted for closure once it is reconciled according to procedures for the appropriate closure method. Two broad categories of closure exist including: (1) Accelerated Case Closure Procedures () and (2) Non- [SAMM , ].
Accelerated Case Closure Procedures
This type of closure allows a to be closed after , even if there are Unliquidated Obligations () on the case. The required international partner funds to pay the are placed in a pending final resolution of the . This program is voluntary, except for those countries that have cases funded by Foreign Military Financing (), which requires mandatory participation in for all cases regardless of the funding source. Most international partners participate or are automatically included in the process. The maintains the master list of international partners that participate in . A list of participants is published in Chapter 3 of the Case Reconciliation and Closure Guide ( Appendix 7) [SAMM ].
A case shall be direct final closed (i.e., not interim closed) if the equals zero, even if supporting contracts remain open. If a contract associated with the case meets the criteria for performance period, litigation status, contract type and contract status, direct final closures should be utilized to the fullest extent possible [SAMM ].
For purchasers in , the aims to close a training case within 36 months of and any other case within 24 months of , as the indicates. If the purchaser wants an case kept open, the request must be approved by the as set out in C16.2.13.2 [SAMM ].
policy requires the purchaser's Ministry of Defense, or an equivalent organization, to agree that the case stays open [SAMM ]. Minutes from a -sponsored financial management review, or a request from an official who holds signature authority, may serve as the purchaser's official request [SAMM ].
cases are marked after the final delivery of defense articles. The Implementing Agencies will then carry out final reconciliation actions and prepare the cases for closure. A partner may submit a for 12 months after delivery of defense articles or services, and a case's entry into status does not by itself stop it from doing so. Once that 12-month period has passed, cases will be closed [SAMM ].
Non-accelerated case closure
Non- procedures are used to accommodate those international partners that have not elected to participate in the process and whose programs are completely financed with (vice with ). case closure always has a higher priority, but non- cases with no supporting contracts should be closed as quickly as possible. Building Partner Capacity () program cases are also closed under non- procedures [SAMM ].
For a non- case, the 12 months between the final delivery of defense articles and closure leave time for final reconciliation actions. They also respect the purchaser's right to submit an on that final delivery. The period runs from the delivery date or passage of title for the defense articles. The date the case entered status does not start it, and entering status does not by itself restrict a partner's ability to submit an . The period can be shortened if the purchaser confirms in writing that it does not expect to submit . E-mail or meeting minutes are acceptable. That statement does not waive the purchaser's right to submit an under the Standard Terms and Conditions ( Figure C5.F8, Section 5.8) [SAMM ].
Closure certificate and closure transactions
The makes sure that the case closure certificate and any other supporting documentation needed, such as closure information for an interim closure, are completed under the established procedures. For those procedures, the manual points to Figure AP7.C4.F5 of the Case Reconciliation and Closure Guide. Every case closure certificate goes by e-mail to the Defense Finance and Accounting Service - Indianapolis () [SAMM ].
Simultaneously with the submission of the closure certificate to the Defense Finance and Accounting Service - Indianapolis (), the must process the “C1” closure transaction for transmission to the . The “C1” transaction signifies completion of its actions necessary for to close the case. This transaction is required for all closure submissions [SAMM ].
Upon successful interface of the C1 transaction, closure data is loaded in the Case Closure Certificate Inventory (CCCI), and applicable closure status/inhibitor codes are assigned. closure status/inhibitor codes and their definitions are contained in Table AP7.C4.T5 [SAMM ]. Other related closure transactions include the “C3,” “C4,” and, “C5.” The “C3” transaction indicates a case is closed. It is generated by and sent to the . The “C4” transaction removes the case from the CCCI. The “C5” transaction reopens a non- case or moves an case from Final to Interim closed status. Both the “C4” and “C5” transactions are initiated by the and sent to [SAMM ].
A “C5” transaction that reopens a non- case requires approval [SAMM ].
reviews the case closure certificate and takes actions to close the case in . If has questions about the closure certificate, contacts the representative listed on the certificate. check the case closure inventory as needed to determine which cases have been closed. should close all cases that do not have any outstanding or unresolved issues within 30 days of closure certificate and acceptance of a “C1” closure transaction [SAMM ].
The estimated closure date
On all cases except I cases, must include a note identifying an estimated case closure date. See , Appendix 6, for exact note wording. Cases with long-running contracts may experience closure challenges, but for cases, the estimated closure date is 24 months after the date of projected final delivery or service performance. For non- program cases, the estimated closure date is estimated to be 36 months after closure of the longest underlying contract (if applicable). If no contracts apply, the closure date should be within 36 months after final delivery or service performance [SAMM ].
Cases implemented on or after October 1, 2017 ( 2018) are also subject to case closure performance standards, which need to be met at the 85 percent level [SAMM ]. The first runs from the CLOSHOLD milestone to the 's submission of the closure certificate, shown by the CLOSE milestone, which follows these estimated closure dates [SAMM ]. The second runs from the complete certificate to final closure, and the Defense Finance and Accounting Service posts the FINCLOSE milestone within 30 days of the certificate [SAMM ].
References
SAMM
- SAMM C16.3: Closure.
- SAMM C16.3.1: Closure Types.
- SAMM C16.3.1.1: Accelerated Case Closure Procedures.
- SAMM C16.3.1.1.2
- SAMM C16.3.1.2: Non-Accelerated Case Closure Procedure.
- SAMM C16.3.9: Closure Transactions.
- SAMM C16.3.9.1
- SAMM C16.3.3: Estimated Case Closure Dates.
- SAMM C16.1.7.1: Case Closure - Posting the Closure Milestone.
- SAMM C16.1.7.2: Preparation for Final Closure.
- SAMM C16.3.1.1.3
- SAMM C16.3.1.1.1.1: Cases are Supply/Services Complete Following Final Delivery.
- SAMM C16.3.1.2.1.1: Case are Supply/Services Complete for at Least 12 Months Following Final Delivery.
- SAMM C16.3.8: Case Closure Certificate.
- SAMM C16.3.9.2
- SAMM C16.3.9.3: Case Closure in Defense Integrated Financial System.
- SAMM C16.1.7: Foreign Military Sales Case Closure Metrics and Performance Standards.
Facts referenced
- ACCP closure goal after Supply/Services Complete, training cases: 36 months (as of 11 September 2026; SAMM C16.3)
- ACCP closure goal after Supply/Services Complete, all cases other than training: 24 months (as of 11 September 2026; SAMM C16.3)
- Months after delivery during which a partner may submit a Supply Discrepancy Report, after which cases are closed (ACCP eligibility): 12 months (as of 28 September 2026; SAMM C16.3.1.1.1.1)
- Months after final delivery before a non-ACCP case is closed (non-ACCP eligibility; reducible if the purchaser confirms in writing that no SDR is anticipated): 12 months (as of 28 September 2026; SAMM C16.3.1.2.1.1)
- Days within which DFAS-IN should close a case with no outstanding or unresolved issues, after the closure certificate and acceptance of a C1 closure transaction: 30 days (as of 11 September 2026; SAMM C16.3.9.3)
- Estimated case closure date written into the LOA, ACCP cases, after projected final delivery or service performance: 24 months (as of 11 September 2026; SAMM C16.3.3)
- Estimated case closure date written into the LOA, non-ACCP cases, after closure of the longest underlying contract: 36 months (as of 11 September 2026; SAMM C16.3.3)
- Months after final delivery or service performance within which a non-ACCP case with no underlying contracts should close (estimated closure date): 36 months (as of 11 September 2026; SAMM C16.3.3)
- Implementation date from which FMS cases are subject to the case closure metrics and performance standards (on or after): October 1, 2017 (FY 2018) (as of 26 October 2026; SAMM C16.1.7)
- Case closure performance standards, share of cases that must meet them (cases implemented in FY 2018 and later): 85 percent (as of 26 October 2026; SAMM C16.1.7)
- Case closure metric two, days from the complete closure certificate within which DFAS posts the FINCLOSE milestone: 30 days (as of 26 October 2026; SAMM C16.1.7.2)
DSCA policy memoranda
- DSCA 26-01: Performance Standards for Foreign Military Sales Case Closure
- DSCA 26-75: Foreign Military Sales Metrics Security Assistance Management Manual Update [SAMM E-Change 845]
Related
Implementing Agency (IA)
The military department or defense agency responsible for the execution of military assistance programs. With respect to FMS, the military department or defense agency assigned responsibility by the Defense Security Cooperation Agency to prepare an LOA and to implement an FMS case. The implementing agency is responsible for the overall management of the actions that will result in delivery of the materials or services set forth in the LOA that was accepted by a foreign country or international organization.
SAMM Glossary, as of 12 September 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
Defense Integrated Financial System (DIFS)
A financial system providing DoD-level financial management functions for the security assistance (SA) program. This includes centralized Foreign Military Sales (FMS) trust fund accounting, foreign customer billing, and financial management reporting. DIFS consolidates FMS data from the Army, Navy, Air Force, and other implementing agencies, and provides efficient accountability for oversight of the financial and program management aspects of SA.
SAMM Glossary, as of 12 September 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
Foreign Military Sales (FMS) Case
A Letter of Offer and Acceptance (LOA) that the purchaser has accepted, together with every Amendment and Modification later made to it: the agreement under which the U.S. Government transfers defense articles and services in the Foreign Military Sales (FMS) program.
FMS Edge glossary, as of 10 October 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
Unliquidated Obligation (ULO)
The amount of obligations that have not been liquidated by payments (disbursements).
SAMM Glossary, as of 12 September 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
Case Closure Suspense Account (CCSA)
Country level account maintained by Defense Finance Accounting Service Indianapolis that summarizes disbursement activity and unliquidated obligation balance for each interim closed case.
SAMM Glossary, as of 12 September 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
FMS: Foreign Military Sale
SAMM Acronyms, as of 12 September 2026
Defense Security Cooperation Agency (DSCA)
The Department of War agency that directs, administers and provides guidance to the Department's components and its representatives at U.S. missions for the execution of the security cooperation programs for which it is responsible [SAMM C1.3.2.2]. The agency also provides financial and technical assistance, arranges the transfer of defense materiel, training and services to international partners, and promotes military-to-military contacts.
FMS Edge glossary, as of 10 October 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
SAMM: Security Assistance Management Manual
SAMM Acronyms, as of 12 September 2026
Glossary entry →Security Assistance Management Manual (SAMM) →
Letter of Offer and Acceptance (LOA)
The legal instrument that lists the defense articles and services, including training, that the U.S. Government transfers to a foreign country or international organization, with their estimated costs and the terms and conditions. The benefitting partner does not sign a Building Partner Capacity (BPC) LOA.
The Letter of Offer and Acceptance (LOA) is the instrument the U.S. Government uses to sell under the Arms Export Control Act (AECA); signed LOAs and their later Amendments and Modifications are also called Foreign Military Sales (FMS) cases [SAMM C5.6.1].
FMS Edge glossary, as of 10 October 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
DSCA: Defense Security Cooperation Agency
SAMM Acronyms, as of 12 September 2026
Glossary entry →Defense Security Cooperation Agency (DSCA) →
LOA: Letter of Offer and Acceptance
SAMM Acronyms, as of 12 September 2026
Supply Discrepancy Report (SDR)
A process for international customers to file a complaint with the DoD for product loss, quality deficiencies, damage, and various other problems associated with the delivery of material under the Foreign Military Sales program.
SAMM Glossary, as of 12 September 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
National Funds
Source of funding that is provided directly from the purchaser.
SAMM Glossary, as of 12 September 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
SDR: Supply Discrepancy Report
SAMM Acronyms, as of 12 September 2026
DFAS-IN: Defense Finance and Accounting Service - Indianapolis
SAMM Acronyms, as of 12 September 2026
DIFS: Defense Integrated Financial System
SAMM Acronyms, as of 12 September 2026
Glossary entry →Defense Integrated Financial System (DIFS) →
Foreign Military Sales Order (FMSO)
A term used to describe Letters of Offer and Acceptance (LOAs) that implement Cooperative Logistics Supply Support Arrangements. Two LOAs are written: a FMSO I and a FMSO II.
SAMM Glossary, as of 12 September 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
Fiscal Year (FY)
The USG’s accounting period. It begins on October 1 and ends on September 30 and is designated by the calendar year in which it ends.
SAMM Glossary, as of 12 September 2026
Glossary entry →Open the manual’s entry → (opens in new tab)
SAMM C16.3: Closure.
“Once a case is Supply/Services Complete (SSC), and the requisite verification steps for SSC reconciliation are complete, the case is eligible to be submitted for closure. Case closure is the final phase of the Foreign Military Sales (FMS) life cycle and is extremely important to the USG and purchaser. Reconciliation for closure involves extensive communication between various logistics, financial and …”
Security Assistance Management Manual, as of 11 September 2026
SAMM C16.3.1: Closure Types.
“Two broad categories of closure exist: Accelerated Case Closure Procedures (ACCP) and non-ACCP. ACCP applies to all countries/programs that have cases financed with Foreign Military Financing (FMF) funds, or those countries that elect to participate. For cases under ACCP all commitments and obligations must be completed, however expenditures do not have to be finalized prior to closure. The non-ACCP category …”
Security Assistance Management Manual, as of 11 September 2026
SAMM C16.3.1.1: Accelerated Case Closure Procedures.
“ACCP is the standard or typical closure process. This type of closure allows a case to be closed after SSC, even if there are outstanding Unliquidated Obligations (ULOs) on the case. Purchaser funds are placed in a Case Closure Suspense Account (CCSA) pending final resolution of the ULOs. This program is voluntary, except for those countries that have FMF-funded cases, …”
Security Assistance Management Manual, as of 28 September 2026
SAMM C16.3.1.1.2
“A case shall be direct final closed (i.e., not interim closed) if the ULO equals zero, even if the supporting contracts remain open. If a contract associated with the case meets the following criteria, direct final closures should be utilized to the fullest extent possible. Performance Period: The performance period of the contract ACRN, CLIN/SLIN of the associated case has …”
Security Assistance Management Manual, as of 28 September 2026
SAMM C16.3.1.1.3
“For purchasers participating in ACCP, the USG goal is to close cases within 36 months of SSC for training cases and 24 months of SSC for all other cases as indicated in the LOA. Should the purchaser want a case to remain open, even though it is SSC, the request must be approved by the IA as outlined in Section …”
Security Assistance Management Manual, as of 28 September 2026
SAMM C16.3.1.1.1.1: Cases are Supply/Services Complete Following Final Delivery.
“FMS cases are marked as Supply/Services Complete (SSC) following final delivery of defense articles. At this time the Implementing Agencies will accomplish final reconciliation actions and prepare cases for closure. A partner may submit an SDR for 12 months following delivery of defense articles/services and is not restricted from doing so simply because a case entered SSC status. After the …”
Security Assistance Management Manual, as of 28 September 2026
SAMM C16.3.1.2: Non-Accelerated Case Closure Procedure.
“Non-ACCP procedures are used to accommodate those countries that have not elected to participate in the ACCP process and whose FMS programs are completely financed with national funds (vice with FMF). While ACCP case closure always has a higher priority, non-ACCP cases with no supporting contracts should be closed as quickly as possible. BPC program cases are also closed under …”
Security Assistance Management Manual, as of 11 September 2026
SAMM C16.3.1.2.1.1: Case are Supply/Services Complete for at Least 12 Months Following Final Delivery.
“The period of 12 months following final delivery of defense articles before a case is closed allows for final reconciliation actions and considers the purchaser's right to submit an SDR associated with the final delivery. The 12-month SDR period is calculated using the delivery date or passage of title for defense articles, not SSC status date. A partner’s ability to …”
Security Assistance Management Manual, as of 28 September 2026
SAMM C16.3.8: Case Closure Certificate.
“The IA ensures the case closure certificate and any other necessary supporting documentation (e.g. ULO closure information for ACCP interim closures) are completed in accordance with established procedures. See RCG Figure AP7.C4.F5. All case closure certificates are sent via e-mail to DFAS-IN (dfas.indianapolis-in.jax.mbx.dfas-in-sca-ccci@mail.mil).”
Security Assistance Management Manual, as of 11 September 2026
SAMM C16.3.9: Closure Transactions.
“Simultaneously with the submission of the closure certificate to DFAS-IN, the IA must process the 'C1' closure transaction for transmission to DIFS. The 'C1' transaction signifies IA completion of its actions necessary for DFAS-IN to close the case. This transaction is required for all closure submissions.”
Security Assistance Management Manual, as of 11 September 2026
SAMM C16.3.9.1
“Upon successful interface of the 'C1' transaction, closure data is loaded in the DIFS Case Closure Certificate Inventory (CCCI) and applicable closure status/inhibitor codes are assigned. DIFS closure status/inhibitor codes and their definitions are contained in the RCG Table AP7.C4.T5.”
Security Assistance Management Manual, as of 11 September 2026
SAMM C16.3.9.2
“Other related closure transactions include the 'C3', 'C4' and 'C5'. The 'C3' transaction indicates a case is closed. It is generated by DIFS and sent to the IA. The 'C4' transaction removes the case from the CCCI. The 'C5' transaction reopens a non-ACCP case or moves an ACCP case from Final to Interim closed status. Both the 'C4' and 'C5' …”
Security Assistance Management Manual, as of 11 September 2026
SAMM C16.3.9.3: Case Closure in Defense Integrated Financial System.
“DFAS-IN reviews the case closure certificate and takes actions to close the case in DIFS. If DFAS-IN has questions about the closure certificate, DFAS-IN contacts the IA representative listed on the certificate. IAs check the DIFS case closure inventory as needed to determine which cases have been closed. DFAS-IN should close all cases that do not have any outstanding or …”
Security Assistance Management Manual, as of 11 September 2026
SAMM C16.3.3: Estimated Case Closure Dates.
“On all LOAs except Foreign Military Sales Order (FMSO) I LOAs, IAs must include a note identifying an estimated case closure date. See Appendix 6 for exact LOA note wording. Cases with long-running contracts may experience closure challenges, but for ACCP program cases, the estimated closure date is 24 months after the date of projected final delivery or service performance. …”
Security Assistance Management Manual, as of 11 September 2026
SAMM C16.1.7: Foreign Military Sales Case Closure Metrics and Performance Standards.
“FMS cases are subject to performance standards and metrics for closure in accordance with DoW FMS Reform Efforts. FMS cases implemented on or after October 1, 2017 (FY 2018) are further subject to specific case closure metrics and performance standards. These metrics and performance standards need to be met at the 85 percent level.”
Security Assistance Management Manual, as of 26 October 2026
SAMM C16.1.7.1: Case Closure - Posting the Closure Milestone.
“The first case closure metric spans from when DSCA posts the Supply/Services Complete (SSC) CLOSHOLD milestone to when the Implementing Agency (IA) submits the case closure certificate to the Defense Finance and Accounting Service (DFAS). The case closure milestone “CLOSE” is posted in the Defense Security Assistance Management System (DSAMS) in accordance with estimated closure dates provided in Section C16.3.; …”
Security Assistance Management Manual, as of 26 October 2026
SAMM C16.1.7.2: Preparation for Final Closure.
“The second case closure metric spans from when the IA submits the complete case closure certificate to DFAS to when DFAS final-closes and accepts the “C8” closure transaction. DFAS posts the FINCLOSE milestone within 30 days of closure certificate in accordance with Section C16.3. The FINCLOSE milestone is created when a transaction is received from DIFS indicating that the case …”
Security Assistance Management Manual, as of 26 October 2026