How is a security cooperation plan resourced?

Updated 26 October 2026Checked against the SAMM: 26 October 2026

Planners resource a plan program by program, laying the activities out over time on a synchronization matrix and estimating costs where funding is not yet known. Each program has its own authorities and submission timelines, and the shortfalls to fund first are weighed by priority, based on risk and urgency. The office's budget submission includes every requirement identified for the partner, whatever its past allocations, and the final Department of War funding recommendations weigh factors such as fiscal constraints, sanctions and schoolhouse capacity.

How is a security cooperation plan resourced?

Planners resource a plan program by program, laying the activities out over time on a synchronization matrix and estimating costs where funding is not yet known.

A synchronization matrix is a simplified picture of how a country-level planner might pull together various () programs into a synchronized plan to achieve a country-level objective (CLO). For example, a notional five-phase plan might aim to help a partner nation secure its border, an identified gap.

In the first phase of such a plan, the , or Senior Defense Official/Defense Attaché (/), and the Law Enforcement Working Group need to build a consensus among the players to support and participate in building this capability. Key Leader Engagements (KLEs) help ensure all sides have buy-in and set realistic expectations. The U.S. Government () may need interagency staff talks to get everyone “on board” and to gather more support or information. If not already accomplished, or not accomplished in enough detail, an additional assessment may need to be conducted. The planners check whether the selected unit can pass vetting requirements. The country may need to change some policies or even laws. If the planner is contemplating using a Building Partner Capacity () program, Congressional Notification will need to take place. The planners also identify any or technology transfer issues to address before moving forward. Finally, the planners might need to work with industry and the implementing agencies to determine production lead times.

During the second phase, the partner nation (PN) needs to continue with individual training, and equipment acquisition, through Foreign Military Financing (), , Direct Commercial Sales (), , or from other agencies. The U.S. may need to conduct Distinguished Visitor Orientation Tours to get PN senior civilian and military personnel to understand the program and cement their buy-in. The PN may need human resources help to attract and retain quality personnel and budgeting training to learn how to budget for this. This is where institutional capability building comes in. This could culminate with the PN participating as observers in a Joint Interagency Exercise.

During the third phase, the PN may need some advanced training. The PN may need logistics and sustainment training to sustain their force. Their support elements might need equipment and training. At this point, the and PN could set up exchanges. This phase could culminate with the PN participating, at a higher level, in another Joint Interagency Exercise.

Additional KLE and military staff talks are conducted during the fourth and fifth phases. These highlight the program’s progress, sustaining support within the PN and the . Simultaneously, the U.S. continues working on interoperability as the PN goes through a certification process and conducts detailed planning for interagency operations.

Planners apply this process to Lines of Effort () and Significant Initiatives (). For such a plan, the planners identify approximate costs and the programs they would like to use to achieve the desired end state five years out, from a mix of interagency and PN funding. Planners need a baseline knowledge of the different programs to identify potential funding sources. If the planners are unsure of existing funding streams, they need to estimate potential costs and work with higher-level policy personnel to identify and forecast resources.

Resourcing is a highly iterative process where the country-level planners determine what will fill gaps. This can be challenging due to competition from higher priority efforts, missed deadlines due to compressed submission timelines, legislative limitations on the lifespan of resources, or because the program is simply a poor fit to the specified program. Each program is specifically designed to address a particular need. Each program has its strengths, and weaknesses, authorities and prohibitions. Planners need to understand these programs and the timelines for submission in order to apply the programs effectively.

The Department of War (DoW) wants to achieve the greatest overall improvement in the specified capabilities with the lowest possible investment. When looking where to invest, the country planner considers the factors listed below.

  • Prioritizing: What shortfalls are most important and pressing? (based on risk and urgency)
  • Deriving: What strategy and environment are the missions and capabilities designed to address?
  • Integrating: Have all services invested, maximizing effectiveness as a joint force?
  • Balancing: Are investments and attendant risk balanced across all the capabilities needed during the planning period?
  • Sequencing: What is needed now? What can wait until later? Is there a logical order in which investments should be made?
  • Resourcing: How much can the afford during the planning period?

Chief among these factors is priority, based on risk and urgency. Risk represents the likelihood of an outcome with negative consequences for shared objectives if resources are not provided, while urgency represents the importance of the resources based on time.

Many factors shape the decisions behind the final funding recommendations that the DoW gives the Department of State. Among them are fiscal constraints, policy and political concerns, sanctions, schoolhouse capacity, how effectively and efficiently earlier funding was used, and whether other funds are available [SAMM ].

Just as the PN has competing requirements and priorities, the also has competing requirements and priorities. To avoid competition, the country planner looks for the “sweet spot,” where the interests of the DoW, the Department of State () (or other agencies), and the PN overlap. The planner also weighs which investments have the broadest payoff and, hence, the most support among the interested parties.

When planning is correct and logical, it justifies program requests as they progress through the chain of command. The country planner should remember that this same prioritization takes place across the theater and at the national level.

At this point, proposed activities, events, operations, and investments are laid out (synchronized) over time. This synchronization serves several purposes. For the planner, it helps determine sequencing and identify critical paths. For the program manager, it helps in requesting resources for future years.

Ideally, the planning timelines take Global Force Management timelines into account. When events are scheduled after the point that forces are requested, either the event adapts to available forces or, ideally, planning timelines are moved to allow for the Request for Forces (RFF) process.

When it drafts budget submissions, the includes every identified requirement of the partner nation, whatever the country's past and International Military Education and Training () allocations have been. A project may be prioritized well outside the country's and budget estimates. Even so, the may keep the whole of the 's budget request in the automated system, so that the 's original submission stays visible to every DoW and Department of State participant in the budget allocation process. By identifying all of the partner nation's requirements in the request, the sets out its priorities and alternatives in case more funds become available [SAMM ].