The is a that pays for defense articles and services ahead of their expected transfer to partners, so they can be delivered in less than the normal . The , in consultation with the Department of State, selects what the fund buys, and it must approve each allocation before the item is added to a . The proceeds of each transfer are paid back into the fund.

What is the Special Defense Acquisition Fund?

The , a , pays for defense articles and defense services ahead of their expected transfer to partners and international organizations. The Secretary of War uses the fund in consultation with the Secretary of [SAMM ].

The , authorized in Section 51 of the , was created to address the issue of long lead times []. The finances the procurement; the articles are transferred under the , the Foreign Assistance Act of 1961 or other law. All assets are transferred to partners using the same laws, regulations, and rules that govern all foreign military transfers [SAMM , , , ].

The provides both procurement authority and funds availability to engage in procurement actions prior to or pseudo- implementation. The allows the U.S. Government () to deliver selected articles and services to partners in less than normal procurement lead-time, and it may preserve U.S. force readiness by reducing the need to divert assets from U.S. forces to meet partners’ urgent requirements [SAMM ].

The is capitalized using selected receipts on sales, as provided in Section 51(b), [SAMM ] [].

When -purchased assets are transferred to a foreign government or international organization, the proceeds from the transaction are reimbursed to the and used to finance subsequent purchases [SAMM ].

Under Volume 12, Chapter 1 of 7000.14-R, the is classed as a Department of War public enterprise fund [SAMM ].

When an purchaser pays with its own for defense articles sold without intent to replace them, the proceeds must be deposited into the . For this rule the manual points to Section 51, and to Volume 3, Chapter 15, section 3.5.6 of the Financial Management Regulation. If the payment comes from U.S. grant assistance instead, including Foreign Military Financing and funds for and activities, the proceeds must go to the U.S. Treasury as miscellaneous receipts under 31 U.S.C. 3302(b) [SAMM ].

Money collected when Department of War (DoW) stock is transferred under a Title 10 authority is not legally authorized for deposit into the . The proceeds of a transfer of equipment that is not intended to be replaced, or cannot be, must be deposited into the Department of the Treasury's miscellaneous receipts [SAMM ].

DoW components identify the items or services proposed for procurement using the funds [SAMM ].

The , in consultation with the Department of State, Bureau of Political-Military Affairs, selects the defense articles and defense services to be purchased by the [SAMM ]. use does not require notification to Congress before funds are executed. , coordinating with the Department of State, is required to give the appropriate congressional committees quarterly spend plans and an annual report on the defense articles and services acquired, possessed and transferred through the in the previous fiscal year [SAMM ].

The Implementing Agencies () execute the purchases of approved items [SAMM ]. procurements must be made in accordance with DoW regulations and procedures, as outlined in the and the Defense Supplement () [SAMM ]. The international agreements exception to does not necessarily apply to an procurement [SAMM ].

The are responsible for storing and maintaining accountability of defense articles purchased by the until the items are transferred to a foreign government, international organization, or Building Partner Capacity program. In addition, the must establish controls to ensure assets are not transferred to an international partner unless explicitly approved by [SAMM ].

An approved allocation request authorizes the to offer the requested item or service to a foreign government, international organization, or Building Partner Capacity program [SAMM ].

The allocation process begins when an eligible foreign country, international organization, or Building Partner Capacity program requests information on defense articles and/or services, and the articles and/or services are available in the inventory. When such a request is received, the should verify the availability of the requested asset and then submit an allocation request to [SAMM ].

-procured assets are allocated in accordance with the laws, regulations, and policies that apply to all and transfers. The allocation of an asset to support an eligible foreign country, international organization, or Building Partner Capacity program must be approved by before it can be added to an [SAMM , ].

Generally, sales are made from assets in the inventory. In instances where the article or service requested has been purchased by the but not yet delivered to the , the international partner may purchase the equity that the owns in the acquisition contract [SAMM ].

assets may be offered on a separate or as one or more separate lines on an that includes articles and services that will not be sourced from the inventory. Sub-lines will not mix and non- material and services [SAMM ]. Once a case is offered, the assets on the case will be held in reserve until the expires [SAMM ].

The price for assets and contract equities sold through the process is computed by starting with the contract unit price and adding proportionate charges for transportation, receipt, storage, maintenance and physical inventory, as applicable [SAMM ]. paid by the are included in the selling price [SAMM ]. A ’s costs for performed for the are built into the unit price, but should not be applied to case lines that include -procured defense articles or defense services [SAMM , ].

The payment for defense articles and services sourced from the must be included in the [SAMM ].

Where the fund came from

The was authorized by Section 108(a), International Security and Development Cooperation Act of 1981, P.L. 97-113, 29 December 1981, to provide the DoW the authority to procure and stock defense articles and services in anticipation of future foreign government military requirements. By permitting such advance procurements, the enabled the DoW to reduce customer waiting times for selected items, improve its response time to emergency foreign requirements, and reduce the need for meeting normal requirements through drawdowns or diversions of defense equipment from U.S. stocks or new production.

The was established as a which was initially capitalized through three sources:

1. Collections from sales of DoW stocks not intended to be replaced

2. Asset use collections and contractor payments for the use of U.S.-owned facilities equipment

3. Recouped non-recurring research, development, and production charges from both and Direct Commercial Sales ()

By 1987, the reached its maximum authorized capitalization level, which represented the total value of articles on hand and on order as well as all unobligated funds. Although appropriated funds were authorized, no appropriations were necessary, as the fund was maintained on a self-supporting basis, with Congress annually providing an for expenditures. served as the overall DoW manager of the , while the Military Departments () retained custody of those articles awaiting sale.

The provided a viable method for effecting advance procurements to reduce customer waiting time as well as a source of urgently needed articles. Operation Desert Storm forces used articles from the stocks, to include AIM-9, STINGER, and TOW missiles, plus various types of vehicles, ammunition, night vision devices, and communications equipment.

A major DoW budget tightening effort in 1991 led to the decision in March 1993 to close down the program. No new was sought for the from fiscal year () 1994, and Congress carried existing OA forward for the purpose of closing the fund, extending it to 2000 []. With drawing to a close, Section 145, P.L. 104-164, repealed a variety of recurring status reports required by Congress under Sections 51 and 53, .

At the Administration’s request, Congress reactivated the in 2012, authorizing the use of existing administrative funding to recapitalize the existing authority [SAMM ].

The operates within limits that Congress sets (see Section 51(b)(1), ). No money in the fund may be obligated unless Congress has first approved an obligation limitation, which appropriation acts set during the annual budget process. Since the fund was reconstituted in 2012, the , Foreign Operations and Related Programs Appropriation Act has provided its each year [SAMM ].

The fund's capitalization limit is set in 10 U.S.C. 114(c). The limit is the fund's original $100M cash balance from fiscal year 2012 plus the total value of the offsetting collections it has received. Under the National Defense Authorization Act for fiscal year 2023 (P.L. 117-263), the limit may not exceed $3.5B [SAMM ] [].

Why buying for a partner takes time

Acquisition in support of , both and Building Partner Capacity (), can sometimes take a long time. Long acquisition lead times can be caused by several different factors.

First, for () programs, there is the lead time. The lead time reflects the amount of time from receipt of the request until the is accepted and financially implemented. The length of this lead time depends on the ’s complexity. For programs, the serves as both the authority and funding source for the acquisition. As a result, even though the partner’s requirements are known early in the overall process, contracting actions cannot proceed until the agreement ( or case) has been accepted and financially implemented.

Second, there is the contracting administrative lead time. The contracting administrative lead time reflects the amount of time required from when the funded requirement is provided to the respective DoW until the procurement contract is awarded to a vendor. The administrative lead time is largely influenced by the time necessary to comply with the many mandatory DoW acquisition policies and procedures. Acquisition in support of is accomplished using the same acquisition policies, procedures, and management infrastructure that are utilized to make purchases for the DoW itself. Some of the actions accomplished during the administrative lead time include thoroughly identifying the requirement; performing to determine source options; developing clear specifications or statements of work/objectives; identifying an acquisition strategy; formulating a plan and evaluation criteria; advertising/soliciting for offers; allowing time for potential vendors to develop offers; evaluating competing offers; conducting discussions with industry to better understand offers; scoring industry proposals based on strengths/weaknesses/risks; selecting the offer that provides the overall best value; and awarding the contract.

Third, there is the manufacturing or . The reflects the amount of time required from date of until the vendor physically delivers the product or service to the . This lead time is largely influenced by the nature of the article or service being purchased. Although some articles or services are readily available, others are intrinsically more complex and take longer to produce. Some actions during the include scheduling new contract work into existing production orders and purchasing raw materials, fabricating parts, assembling components, integrating subsystems, performing final assembly, inspecting, and testing. This period of time can substantially lengthen if the article or service deviates from the DoW standard specifications or configurations which necessitates additional design, integration and testing services.

Fourth, there is the transportation lead time. The transportation lead time reflects the amount of time necessary to physically move the article from the point of origin, typically somewhere within the continental U.S. to the final destination within the partner’s country. For services, this increment of time reflects the time for the contractor to select employees, prepare the work team, forward materials, and deploy the team to the partner’s country. The transportation lead time depends on the mode of transportation for articles or the availability of personnel for services.

As a result, the cumulative lead time for an item sourced from procurement is the sum of the following:

  • lead time ( to financial implementation)
  • Contracting administrative lead time (to )
  • (to manufacture or assemble the article)
  • Transportation lead time (to the final location in the partner’s country)

Together, these can result in a lengthy overall lead time until delivery.

References

SAMM

Public authorities

  • AECA §51: Arms Export Control Act of 1976, as amended, §51 (22 U.S.C. §2795), Special Defense Acquisition Fund
  • §536, P.L. 105-118: Foreign Operations, Export Financing, and Related Programs Appropriations Act, 1998, Pub. L. 105-118, §536
  • 10 U.S.C. §114: 10 U.S.C. §114, Annual authorization of appropriations