Can a purchaser inspect Excess Defense Articles before transfer?

Updated 26 October 2026Checked against the SAMM: 26 October 2026

Yes. Partners are encouraged to inspect before delivery in a Joint Visual Inspection, which the partner requests in writing from the and attends at its own cost. The must give the and the Department of State written notice at least 30 days before the inspection, and an inspection is not a promise to transfer the item.

Can a purchaser inspect Excess Defense Articles before transfer?

Partners are encouraged to inspect before delivery, and a partner can hold the inspection either before or after the transfer has been authorized. This inspection is called a Joint Visual Inspection (). A partner requests one in writing from the appropriate , and partners must pay for their own participation [SAMM ].

The must give the and the Department of State written notice at least 30 days before it conducts the . This gives and a chance to confirm that holding the is in line with U.S. national security and foreign policy. The notice must name the partner, the items to be inspected and the known or approximate dates of the . The must send it by email to the Department of State's Bureau of Political-Military Affairs (), the Program Manager and the Country Portfolio Director. When a comes before the transfer has been authorized, the must make every reasonable effort to have the partner understand that the inspection is not a promise or guarantee by the U.S. Government to transfer the item inspected [SAMM ].

A of the materiel cannot occur before approves the transfer unless the () Country Portfolio Director and (SPP) have granted an exception. Purchasers are encouraged to carry out a before accepting the materiel, and where possible before they receive the . Known limitations in the materiel's condition must be shown on the with the codes in Figure C5.F10 or in unique case notes, and the should state that the "as-is" price does not include the cost of any rehabilitation [SAMM ].

U.S. forces can develop unforeseen urgent requirements for excess items after the items are offered to a partner but before title to them has passed. When items already offered are no longer available, the must notify both and the Under Secretary of War for Policy's office (OUSW(P)). The offer is withdrawn only after OUSW(P) has had the chance to weigh the potential damage that cancelling the transfer would do to national security and foreign policy goals against the U.S. requirements. If OUSW(P) agrees that the U.S. requirements outweigh that damage, will advise the Department of State that the offer is being withdrawn. If OUSW(P) determines that the potential damage to foreign policy goals is not outweighed by the U.S. requirements, the issue will be elevated to the Secretary of War for decision under the procedures in Section C6.4.6 [SAMM ].